Chronology of events for SWM works

    * Agreement Signed on 06.03.08.
    * Contract Period 18 months.
    * Contract Amount Rs. 4, 92, 39,711/-.
    * Completion date 05.09.09.
    * Completion date extended upto 31-12-09
    * Financial Progress till date Rs.17,48,378/-(3.55%).

PROGRESS OF SWM WORKS

    * New land fill segment B – Ready for laying clay liner and HDPE liner. Supply of HDPE liner partially completed. Sanction awaiting from RDO for clay mining.
    * Reengineered land fill in segment A – Agreed quantity almost completed and ready for capping.
    * Civil Works – Compost processing area, workshop office, workers’ rest room, weigh bridge cabin completed except flooring and petty works etc.
    * Go down – Columns work completed. ISM work, roofing, solid block masonry works and flooring to be completed. Fabrication works going on.
    * Weigh bridge – Erection in progress.
    * Leachate pit at compost plant completed except plastering.
    * Drain –525 m length almost completed along the existing road side - the work is nearing completion.
    * Drain around new land fill site (segment B), earth work excavation and PCC completed. RR masonry started. Drain work at reengineered land fill site to be started.
    * Electrical works – To be started.
    * Mechanical works – To be started. Supplied 16 mm sieves.
    * Leachate plant – To be started.
    * Road formation in segment B - Road section formed – GSB, DBM etc to be done. Road formation in segment A started.
    * Green Belt – 55 saplings planted in Segment B. Balance 90 to be planted in Segment A.
 

DRAIN WORK AT LALOOR
 
LEACHATE PIT
 
 
 
       
EARTHWORK EXCAVATION FOR DRAIN IN SEG-B AT LALOOR