Roads

URT WORKS

Chronology of events for URT works

    * Agreement Signed on 25.03.2008
    * Contract Period 18 months, extended by another 4 months.
    * Contract Amount Rs.28,27,47,265/-, extended
    * Completion Date 24-10-09, extended upto 28-02-2010 by supplementary agreement signed.
    * Financial Progress till date Rs. 20, 13, 50,171 (65%).
    * 1st variation order dated 25-10-2008 for Rs. 28,43,780/- (1% above)
    * 2nd variation order dated 19-11-2008 for Rs. 1,33,60,499/-(5.73 % above)
    * 3rd variation order dated 14-05-09 for Rs. 1,09,84,802/- (3.89 % above)
    * Over all amount of contract as on 30-09-09 Rs. 30,99,36,346/- (9.62 % above)
    * 4th Variation order prepared and put up for approval by CLSC Rs. 1,40,06,802/-. 4.34 % above and revised amount stands to Rs. 32, 46, 43,149/- including utility shifting.

PROGRESS OF URT WORKS

    * Bituminous works completed in all roads except Swaraj Round and part of M.O.Road in front of corporation office.
    * Drain works, new drains and raising of existing drains completed for a length of 13000 m (New drain 7500 m, rising of walls 5500 m) and cover slab laid 8030 m. New proposal along Swaraj Round, P.O.Road and Kuruppam Road to be finalized.
    * Shoulder filling using earth in Shornur Road completed and that in KSRTC–Fathima Nagar Road completed.KSRTC-Koorkenchery Road completed but to be replenished where the rain has washed off the filling. Chiyyaram-Koorkenchery Road completed.
    * Subway at Paramekkavu junction completed and commissioned.
    * High mast lights work completed 4 nos. and commissioned.
    * Kerb fixing completed in Shornur Road, KSRTC-Fathima Nagar Road except the few gaps now being done, KSRTC-Koorkenchery road completed. P.O.Road almost completed. M.O.Road still to be started near the Swaraj Round. Kuruppam Road, P.O.Road and Swaraj Round to be done.
    * Footpath construction - KSRTC- Fathima Nagar road nearing completion.
    * Planting of avenue trees – 49 nos. - work completed (estimate provision)
    * Hedges planting – 120 m - work completed.
    * Painting kerb completed in KSRTC-Fathima Nagar Road and P.O.Road. The work is in progress along KSRTC-Koorkenchery, Kuruppam Road, M.O.Road extension and Shornur Road.
    * Electric posts – positions located – 50 posts supplied. 41 posts erected. Cable laying started along M.O.Road and M.O.Road extension.
    * Road sign board– 118 posts erected. Work completed in KSRTC-Fathima Nagar Road, KSRTC-Koorkenchery and Chiyyaram-Koorkenchery and in M.G.Road, Swaraj Round, P.O.Road to be started. Construction of median and the filling inside also completed along M.O.Road, M.O.Road extension and KSRTC-Fathima Nagar. 83 road direction boards supplied and erection will be started by 10-12-09.

 

ROAD WORK AND TILING WORK COMPLETED AT FATHIMA NAGAR ROAD
 
 
 
       
CROSS DRAINAGE ALONG SWARAJ ROUND