WATER SUPPLY
- Agreement executed with Contractor – Package No. TSR-WS-01.
- Accepted amount is Rs. 42,18,18,118/-
- Joint Account opened with Superintending Engineer, KWA & Secretary, Thrissur Corporation.
- Total payment released to the Contractor Rs. 8,21,52,196/-(including mobilization advance Rs. 4,21,81,812/- )
- 14.78 km of 700 mm DI pipe collected at site.
- 9.45 km pipe laying completed.
- Field pressure testing 8 reaches completed. Total length 3.8 km.
- Chemical house renovation works completed.
- Chipping and replastering of one flocculator and one clariflocculator completed.
- Chipping and replastering of filter bed, channels, trough, manifold channels completed. Laying of manifold cover slab completed.
- Tiles laying of one filter chamber completed.
- Chipping of roof slab of WTP is in progress.
- 110 mm 10 kg pipe supplied, laying work started for laterals.
- Filter media partially received.
- DPR of distribution network discussed with Supt.Engineer, KWA and corporation steering committee. Revised DPR preparation is in progress.